31st May 2024
Futureproof Clare, a grassroots environmental group campaigning for social and environmental justice, has joined forces with concerned individuals in a judicial review against the recently approved Ennis data centre and power plant campus.
Read our full press release here.
14th April 2024
Futureproof Clare (FPC) is genuinely disgusted at the decision of An Bord Pleanála to grant permission for the construction of six data centre halls on the outskirts of Ennis. The 200 MW data centre complex will use as much electricity as 200,000 homes, and has been granted permission to build a 120MW gas plant to supply its energy. In addition, the data centre plans to use an additional 80 MW from the already strained Eirgrid. Futureproof Clare will deliberate on how it will continue to campaign against An Bord Pleanala’s decision. We call on an members of the public who are not happy with the decision to grant permission to this unsustainable development to contact us via futureproofclare@gmail.com
Full statement here.